Machining of the wheel coat after reloading
In June 2023, we worked on the G1 Group (Kaplan type) of the Villerest Hydroelectric Power Plant, in France, for our customer EDF.
Remanufacture the cylindrical and spherical part of the existing wheel mantle after reloading to return to the original shape and ribs. The portion to be taken back extended over a height of about 1000mm.
Β
Our intervention took place in several stages:
The intervention is identical to that of the Fessenheim wheel mantle, but on a smaller diameter. A smaller machine was therefore used for this operation.