Site preparation

Published on 04/12/2023

𝑺𝒊𝒕𝒆 𝒑𝒓𝒆𝒑𝒂𝒓𝒂𝒕𝒊𝒐𝒏 🚧

𝘉𝘦𝘩𝘪𝘯𝘥 𝘵𝘩𝘦 𝘴𝘤𝘦𝘯𝘦𝘴 𝘱𝘳𝘦𝘱𝘢𝘳𝘢𝘵𝘪𝘰𝘯𝘴 𝘰𝘧 𝘰𝘶𝘳 𝘵𝘸𝘰 𝘭𝘢𝘳𝘨𝘦𝘴𝘵 𝘮𝘢𝘤𝘩𝘪𝘯𝘪𝘯𝘨 𝘮𝘢𝘤𝘩𝘪𝘯𝘦𝘴 𝘰𝘯 𝘴𝘪𝘵𝘦

𝘈 𝘴𝘮𝘢𝘭𝘭 𝘸𝘪𝘯𝘬 𝘧𝘰𝘳 𝘐𝘴𝘢𝘣𝘦𝘭𝘭𝘦 𝘸𝘩𝘰 𝘳𝘦𝘴𝘶𝘮𝘦𝘴 𝘴𝘦𝘳𝘷𝘪𝘤𝘦

Intervention on stator of group G1 𝘝𝘐𝘓𝘓𝘈𝘙𝘖𝘋𝘐𝘕

Villarodin hydroelectric power station, France

Intervention on Stator of group G1

Our teams are currently working on the G1 group stator carcass of the Villarodin Hydroelectric Power Plant, in France, for our customer JEUMONT ELECTRIC.

  • Complete destruction of 50 key bars by milling (3.2 m high) respecting a rib established by the customer relative to the axis of the carcass
  • 800 M10 drilling and tapping for fixing new bars
  • Rib of bars machined relative to carcass axis: 0.1 mm

Our intervention took place in several stages:

  • Step 1: Analysis of the subject in our Design Office (feasibility, implementation of our machines in the 3D working environment).
  • Step 2: Carrying out pre-work checks (Laser Tracker) by an external company.
  • Step 3: Installation of our machine on site and machining.
  • Step 4: Realization of after-work checks (Laser Tracker) by an external company.

3D MODELLING

The implementation of our machines in 3D

MACHINE SETUP & MACHINING